GSA Form 184B: Construction Progress Report (Modification/Change Order Breakdown)

GSA Form 184B prints the heading Construction Progress Report (Modification/Change Order Breakdown). GSA's forms page lists it as Construction Progress Report (Change Order Breakdown), with a current revision date of 10/2016 and the authority or regulation PBS 2800.16. The footer reads GENERAL SERVICES ADMINISTRATION, and GSA hosts it in its forms library.

The instructions on the back say GSA 184B is prepared by the contracting officer or an authorized representative, and is used on all construction contracts awarded under new construction, repair and alteration programs, regardless of Delivery Method. The form says it provides part of the necessary documentation on construction progress and that a copy is completed promptly prior to payment requests.

Each row is one modification, with five columns in dollars only: modification number, total value of the modification, value of work completed (previous and current), value of materials, and total value of completed work. You can fill it out free in your browser on this page and download the result without an account.

Top of page 1 of GSA Form 184B: Construction Progress Report (Modification/Change Order Breakdown), as printed by GSA

What's on GSA Form 184B

Header: page, report number and date

Page and number of pages, the report number and the date.

Contract identification

The contract number and the task order number.

Columns 1 and 2: modification and its value

The modification number and the total value of the modification in the contract, in dollars only.

Column 3: value of work completed

Sub-column (a), previous value, is the cumulative amount completed through the previous report. Sub-column (b), current value, is the amount completed since the previous report.

Column 4: value of materials

The value of stored materials during the construction phase, in dollars only.

Column 5: total value of completed work

The value of work in place and stored materials for each modification.

How to complete GSA Form 184B

  1. 1

    Fill in the header

    Enter the page count, report number and date, then the contract number and task order number.

  2. 2

    List each modification

    Enter the modification number in Column 1 and the total value of the modification in the contract in Column 2.

  3. 3

    Enter work completed

    In Column 3, enter the cumulative amount completed through the previous report in sub-column (a) and the amount completed since the previous report in sub-column (b).

  4. 4

    Add materials and the total

    Enter the value of stored materials in Column 4 and the value of work in place and stored materials in Column 5.

  5. 5

    Keep it current

    The form says a copy is completed promptly prior to payment requests and that the information on it is kept current.

Why fill Form GSA184B on indox

You get the real form, filled in a browser tab, with nothing standing between you and the finished PDF.

  • Fill the form right in your browser, no software to install
  • Free to fill and free to download, with no account
  • The official blank straight from the GSA, not a copy someone retyped
  • Works on a phone, tablet or computer

Routing and what the form says

Where it goes

The form prints no address or routing. It says the GSA Form 184B provides part of the necessary documentation on construction progress.

When it is completed

The form says a copy is completed promptly prior to payment requests, and the information on it is kept current.

Authority

GSA's page lists the authority or regulation as PBS 2800.16.

Form name and edition

GSA's page lists the title Construction Progress Report (Change Order Breakdown). The PDF heading reads Construction Progress Report (Modification/Change Order Breakdown), and the footer reads GSA 184B (REV 10/2016). It prints no OMB number or privacy statement.

Who fills out GSA Form 184B?

  • The contracting officer

    The form says GSA 184B is prepared by the contracting officer.

  • An authorized representative

    The form says the contracting officer's authorized representative may prepare it instead of the contracting officer.

  • Construction contracts it covers

    The form says it is used on all construction contracts awarded under new construction, repair and alteration programs, regardless of Delivery Method.

  • Contracts with modifications

    Each row is for one modification number, with the total value of that modification in the contract and the work completed against it.

The instructions on the back of the form say who prepares it and which contracts it covers.

Official sources and the blank

Do it all with indox

View all 94 tools

Questions about Form GSA184B

Who issues GSA Form 184B?

The footer reads GENERAL SERVICES ADMINISTRATION and GSA 184B (REV 10/2016). GSA hosts it in its forms library, and its page lists the authority or regulation as PBS 2800.16.

Who prepares GSA Form 184B?

The form says it is prepared by the contracting officer or the contracting officer's authorized representative.

When is GSA Form 184B completed?

The form says a copy is completed promptly prior to payment requests and that the information on it is kept current.

What goes in each row of GSA Form 184B?

One modification: its number, the total value of the modification in the contract, the previous and current value of work completed, the value of stored materials and the total value of work in place and stored materials.

What is the difference between previous value and current value?

The form says sub-column (a) is the cumulative amount completed through the previous report and sub-column (b) is the current amount completed since the previous report.

Is it Change Order Breakdown or Modification/Change Order Breakdown?

GSA's forms page lists GSA184B as Construction Progress Report (Change Order Breakdown). The PDF on that page prints the heading Construction Progress Report (Modification/Change Order Breakdown). The page gives no reason for the difference.