Building, PBS job number, sheet number of total sheets, agency and order number, description of work, and how the work is to be accomplished.
GSA1814
Job Order Control
GSA Form 1814, Job Order Control, is a two-page General Services Administration (GSA) form, printed as GSA FORM 1814 (REV. 6-71). GSA hosts it in its forms library, and GSA's page lists PBS P 5800.18B as its authority or regulation and a current revision date of 06/1971.
The front page identifies a job by building, PBS job number, agency and order number, and description of work, with boxes for work to be accomplished by force account, contract or a combination. It has a summary of estimates for hours, hourly rates, labor and material cost by trade, contract costs, a general expense cost percentage and total costs, then the actual job cost and a running log of man-hours charged and dollar cost with an estimated percent complete. The back has a cost record of materials used and a record of contract and other costs.
The PDF prints no instructions and does not say who completes, signs or receives the form. You can fill it out free in your browser on this page and download the result without an account.

Building, PBS job number, sheet number of total sheets, agency and order number, description of work, and how the work is to be accomplished.
Number of hours, hourly rate, labor cost and material cost by trade, then contract costs, subtotal, a general expense cost at a stated percent, and total costs. The heading says to attach all backup details.
Date started and date completed, then actual labor, material, contract, subtotal, general expense and total cost.
A running log of man-hours by trade with a total, dollar cost for labor, material and contract with a total cumulative, and an estimated percent complete, with a total row.
A cost record of materials used and a record of contract and other costs, each with date, source, remarks and amount columns and a total line.
Enter the building, PBS job number, sheet number, and agency and order number. The PBS job number also appears at the top of the back page.
Write the description of work and mark force account, contract or combination.
Fill in hours, rates and costs by trade, contract costs, the general expense percent and the totals. The form says to attach all backup details.
Record man-hours charged by trade, dollar cost for labor, material and contract, the total cumulative and the estimated percent complete.
On the back, list each material and each contract or other cost by date, source, remarks and amount, and total each table.
Enter the date completed and the actual job cost for labor, material, contract, general expense and total.
The PDF has no instructions. These steps follow the order of its blocks.
You get the real form, filled in a browser tab, with nothing standing between you and the finished PDF.
The PDF gives no filing address and names no office that receives the form.
The Summary of Estimates heading says to attach all backup details.
The PDF prints no instructions, signature lines, OMB number, time estimate or Privacy Act statement.
GSA's page lists form number GSA1814, a current revision date of 06/1971 and PBS P 5800.18B as the authority or regulation.
The PDF does not say who completes the form, who signs it or which office receives it.
The header has a line for Agency and Order No., next to the building and the PBS job number.
Boxes under Work To Be Accomplished By show whether the job is done by force account, by contract or by a combination.
The estimate and man-hours columns are headed Estimated, Carpenter, Electrician and Painter, with blank columns for other trades.
The form has no instructions and no signature lines. These are the parties and entries its blocks name.
The agency’s own page for Form GSA1814.
The official blank form, to print or fill by hand.
No tool matches that search.
The footer reads GENERAL SERVICES ADMINISTRATION and GSA FORM 1814 (REV. 6-71). GSA hosts it in its forms library.
The PDF does not say. It has no instructions and no signature lines, and names no office that completes or receives it.
Estimated and actual labor, material and contract costs, a general expense cost at a stated percent, and the totals, plus man-hours by trade.
A cost record of materials used and a record of contract and other costs, each listed by date, source, remarks and amount with a total.
The header has a Sheet __ of __ box, and the back repeats the PBS job number.
GSA's page lists PBS P 5800.18B as the authority or regulation and 06/1971 as the current revision date.