GSA Form 220: Inspection Report on Work Under Contract

GSA Form 220, Inspection Report on Work Under Contract, is a General Services Administration form, Rev. 9/2025. GSA hosts it in its forms library, and GSA's page lists the PBS Project Management Guide as its authority. GSA's listing titles it Inspection Report for Work Under Contract.

The instructions on the back say GSA 220 is used for documenting contract compliance by the Contracting Officer's Representative (COR) on all construction contracts awarded under new construction and repair and alteration programs. The form says it documents the required separation of duties between the ordering and inspecting functions, and that the COR is the GSA responsible party for accepting the work for payment purposes.

The front has 26 numbered blocks covering the contract, prices, completion dates, the firms and inspector involved, the inspection and the COR's approval. The back holds the instructions, the final inspection procedure, reinspection costs and a definition of substantial completion. You can fill it out free in your browser on this page and download the result without an account.

Top of page 1 of GSA Form 220: Inspection Report on Work Under Contract, as printed by GSA

What's on GSA Form 220

Blocks 1 to 8: contract and contractor

Contract or task order number, location (street, city and state), building, contractor's name and address, type of work, whether the contract is for repair and alterations or new construction, project or invoice number, and date of notice to proceed.

Blocks 9 to 12: prices and liquidated damages

Original contract price, cumulative change orders or modifications, contract price to date, and liquidated damages per day, each in dollars.

Blocks 13 and 14: completion

Contract, revised, estimated and actual completion dates, and the actual and normal percentage of completion.

Blocks 15 to 18: firms and inspector

Architect-engineer (A-E) firm, construction manager (CM) firm, construction manager as agent (CMa) engineer and GSA inspector.

Blocks 19 to 24: the inspection

Type of inspection (progress, substantial completion, final or post final), dates of the last inspection and this inspection, and yes or no boxes for additional inspections, payment and retainage recommended.

Blocks 25 and 26: condition and COR approval

The general condition of the work, labor force, delays or corrective actions, recommendations, change orders or modifications, percentage of completion and a description of work with related CLINs or Sub-CLINs, then the COR's name, signature and date.

How to complete GSA Form 220

  1. 1

    Fill in the contract details

    Complete blocks 1 to 18 with the contract, building, contractor, prices, completion dates, percentages and the firms and inspector involved.

  2. 2

    Mark the type of inspection

    Check PROGRESS, SUBSTANTIAL COMPLETION, FINAL or POST FINAL in block 19, then enter the dates of the last inspection and this inspection in blocks 20 and 21.

  3. 3

    Record the recommendations

    Answer yes or no in blocks 22 to 24 for additional inspections, payment and retainage recommended.

  4. 4

    Describe the work in block 25

    State the condition of the work, the labor force, delays or corrective actions, change orders or modifications since the last inspection and the percentage of completion, with a description of work and related CLINs or Sub-CLINs.

  5. 5

    Follow the final inspection procedure

    For a final inspection, the instructions say to give the contractor a list of items to correct, send the Building Manager a copy of the letter, forward the final report and lists to the Regional Office, and indicate the date the work was substantially completed.

  6. 6

    COR signs block 26

    The COR enters a name, signs and dates the COR APPROVAL block.

Why fill Form GSA220 on indox

You get the real form, filled in a browser tab, with nothing standing between you and the finished PDF.

  • Fill the form right in your browser, no software to install
  • Free to fill and free to download, with no account
  • The official blank straight from the GSA, not a copy someone retyped
  • Works on a phone, tablet or computer

Where it goes and what the form says

Final report to the Regional Office

The instructions say to forward to the Regional Office the final report, three copies of the list of defects and omissions given to the contractor, and a SEPARATE supplementary statement in duplicate with an estimated cost of completing each item.

Supplementary statement

Items whose completion is not practicable go in the supplementary statement, with a recommendation on the amount, if any, to be deducted from the contract price. The form says it should NOT be given to the contractor or the Building Manager.

Reinspection costs

The form points to General Conditions provisions on contractors' written notices of readiness for final inspection and liability for reinspection costs. Costs of extra final inspections are forwarded in separate statement form.

Substantial completion

The form defines it as the date the facility, project or service, or a part of it, can be operated or occupied for its intended use, even if minor repairs or punch list items are still needed, and refers to the Project Management (PM) Guide.

Not a public filing

The form covers GSA construction contracts. The PDF prints no OMB number, burden statement or privacy notice.

Who uses GSA Form 220?

  • Contracting Officer's Representative (COR)

    The instructions say the COR documents contract compliance with the form, makes sure required inspections are performed and that the work meets contract requirements, and accepts the work for payment purposes. The COR signs block 26.

  • Construction manager advisor

    The form says the COR may inspect the work or may oversee the inspection by an independent 3rd party construction manager advisor contract employee. Block 17 names the CMa engineer.

  • GSA inspector and firms

    Blocks 15 to 18 name the architect-engineer (A-E) firm, the construction manager (CM) firm, the CMa engineer and the GSA inspector.

  • Contracting Officer, Building Manager and Regional Office

    After a final inspection, the instructions say the Building Manager gets a copy of the letter to the contractor, the Contracting Officer decides on items that may remain as installed, and the final report goes to the Regional Office.

  • The contractor

    Block 4 records the contractor's name and address. After a final inspection, the instructions say the contractor gets a list of items needed to complete the contract, but not the supplementary statement.

The form is used by GSA staff on GSA construction contracts. The instructions and blocks name these people.

Official sources and the blank

Do it all with indox

View all 94 tools

Questions about Form GSA220

Who fills out GSA Form 220?

The instructions say the Contracting Officer's Representative (COR) uses it to document contract compliance. The COR may inspect the work or oversee the inspection by an independent 3rd party construction manager advisor contract employee, and signs block 26.

What contracts does GSA Form 220 cover?

The instructions say it is used on all construction contracts awarded under new construction and repair and alteration programs.

What inspection types can be marked?

Block 19 lists PROGRESS, SUBSTANTIAL COMPLETION, FINAL and POST FINAL.

What does the form mean by substantial completion?

It says substantial completion is the date the facility, project or service, or a part of it, can be operated or occupied for its intended use, even if minor repairs or punch list items are still needed. It adds that entering that date in RETA does not mean financial closeout has occurred.

Who receives the supplementary statement?

The instructions say it goes to the Regional Office in duplicate with the final report, and should NOT be given to either the contractor or the Building Manager.

How is GSA Form 220 different from GSA Form 219?